INFRASTRUCTURE: VILLAS
villas
villas villas villas villas villas villas villas

The substructure and superstructure structural elements including the concrete roof slab, structural steel roof framing, external and internal blockwork walls are complete. Walls have been plastered, but not painted. Cold and hot water reticulation pipework and waste pipework are in place. Electrical conduit and wiring installation including telephone are also built into the structure. Drainage including septic tank, soak pit and inspection chambers are complete. Each septic tank is built and designed for 30 people. All drains were in and for all, flush boxes in place. Leaching fields were in place for all and for each unit there are two (indoor and outdoor) spa pools, bathrooms, toilets, etc.
b) Building #2 Bure Type B Standard – Status as for Building #1 plus dwarf wall capping not done
c) Building #3 Bure Type A Reverse – Status as for Building #1
d) Building #4 Bure Type B Reverse – Status as for Building #1
e) Building #5 Bure Type A Standard – Status as for Building #1 plus dwarf wall plaster finish and capping not done
f) Building #6 Bure Type B Standard – Status as for Building #5
g) Building #7 Bure Type A Reverse – Status as for Building #1 plus external plaster and dwarf wall capping not done. Internal plaster work has started and approximately 25% done.
h) Building #8 Bure Type A Standard – Status as for Building #1 plus TV internal wall, external plaster and dwarf wall capping not done. Internal plaster work has started and approximately 10% done.
i) Building #9 Bure Type B Standard – Status as for Building #1 plus external plaster and dwarf wall capping not done. Internal plaster work has started and approximately 10% done.
j) Building #10 Bure Type B Reverse – Status as for Building #9 plus stonework not done.
k) Building #11 Bure Type A Reverse – Status as for Building #1 plus external and internal plaster, dwarf wall capping, stonework and bath framing not done. Main entry attached column reinforcing is in place but no formwork. The septic tank is 75% finished with the soak pit dug.
l) Building #12 Bure Type B Reverse – The only substructure work done are the foundation beam, footing, column pad and column. The superstructure concrete columns, beam, roof slab, structural steel roof framing and approximately 50% external blockwork wall have been done. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure have started.
m) Building #13 Bure Type B Standard – The only substructure work done are the foundation beam, footing, column pad and column. The superstructure concrete columns, beams, roof slab, 50% of structural steel roof framing and approximately 10% external blockwork wall have been done. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure have started. The balance of the structural steel framing is on site.
n) Building #14 Bure Type A Standard – The site clearance is roughly 60% done. The only substructure work done are the foundation beam, footing, column pad and column. The superstructure concrete columns, beams, roof slab and structural steel roof framing have been done. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure have started.
o) Building #15 Bure Type A Reverse – Status as for Building #14
p) Building #16 Bure Type B Standard – The only substructure work done are the foundation beam, footing column pad and column. The superstructure concrete columns, 30% beams and roof slab have been done. Also the balance of the concrete beams have reinforcing in place but with no formwork and concrete. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure have started.
q) Building #17 Bure Type A Standard – The site clearance is roughly 60% done. The only substructure work done are the foundation beam, footing, column pad and column. The superstructure concrete columns are done with beam reinforcing in place but with no formwork and concrete. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure have started.
r) Building #18 Bure Type B Reverse – This building is a modification of the Type B Bure version with part of the ground floor slab suspended over the cliff edge into water below. Substructure work over this suspended ground floor slab portion has started.
s) Building #19 Bure Type B Standard – Status as for Building #17
t) Building #20 Bure Type B Reverse – Status as for Building #17
u) Building #21 Bure Type C2 (Manager & Director). All the substructure work have been done except the concrete floor slab. The superstructure concrete columns, beams, roof slab, 25% of structural steel roof framing, external blockwork wall and 75% of internal blockwork wall have been done. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure and drainage work have started and in progress. The balance of the structural steel roof framing are on site.
v) Building #22 Bure Type C1 at Turtle Cove – The site is prepared but no construction work has started.
w) Building #23 Bure Type A at Turtle Cove – The site is prepared but no construction work has started.
x) Building #24 Bure Type C2 (J & S Residence) – No site preparation and construction work done.
y) Building #25 Main Building Complex – All the substructure work are done except the concrete floor slab from the Porte Cochere to the Main Building Complex. The superstructure concrete columns, beam, roof slab, structural steel roof framing, external and internal blockwork wall are all done. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure are complete. External and internal plaster work including Drainage work have started and in progress.
z) Building #26 Activity Bure – All the substructure work are done except the concrete floor slab. The superstructure concrete columns, beams, structural steel roof framing, external and internal blockwork wall are also complete. Cold water and hot water reticulation pipework, waste pipework, electrical conduit and wiring installation built into the structure are complete.